This project is scheduled to be completed in December 2024. A broad sketch of key milestones appears below, with the key date of 7/1/2024 when Workday will go live.

Program timeline

High-level milestones

Line art image of a power button

Develop charter, build team, ancillary disposition determination and plans (iterative process through October 2022)

Line art image of a power button

Develop interfaces (iterative process through June 2024)

Line art image of a power button

Build solutions (iterative process through June 2024)

Line art image of a power button

Integrate ancillary systems with new interfaces (iterative process through June 2024)

Line art image of a power button

Develop integrations with Workday (iterative process through June 2024)

Line art image of a power button

Deliver, support

Line art image of a power button

Program complete